UPDATE FROM TAYLOR WIMPEY
The Parish Council has received an update from Taylor Wimpey today regarding the site at Squires Cross.
Please see below:-
‘Taylor Wimpey will be taking over as Principle Contractor on the site from 8th September. The Site Manager will be Mark Degville.
The first round of piling works is complete for the plots nearest to the southern boundary.
Drainage works have been ongoing within the site as well as offsite and the works to connect the two are happening this week and potentially into the start of next week.
We are aware of some claims that our groundworkers and suppliers have been breaching the Construction Management Plan working hours and traffic management and we have reminded everyone of the restrictions. We are happy to continue to receive reports of any further breaches so that we can follow up with the relevant party. As you can imagine, it is difficult to ensure the communication is passed down to every third party but rest assured we are doing as much as we can to facilitate this.
The Public Right of Way closure has been extended to the 1st September 2026 and the new notices will be going up on Monday afternoon. As previously mentioned, we will open the right of way as soon as it is safe to do so and do not expect that it will be closed for the full year.
We will be opening a temporary sales cabin towards the end of September, with delivery of this expected on the 15th September.’