TAYLOR WIMPEY DEVELOPMENT

The Parish Council strive to keep to a channel of communication with Taylor Wimpey and request regular updates from them. When/if those updates are received the Parish Clerk will share them with village via the website and other appropriate mediums.

The latest update is listed below which is the anticipated schedule of activity on the site:

  • Laying off-site gas mains (approx. 10m) 27th-30th Jan 2025
  • Electric Mains Installation:
    10th-21st March 2025 (Squires Road and Plott Lane)
    7th-18th April 2025 (Orchard Way – to connect to substation – and Squires Road)
  • Tree Works: They anticipate work commencing 10th Feb for 5 days to clear space to form the entrance to the site and remove trees marked for removal within the planning drawings.
  • GCN trapping: They have a license to trap the site out which ensures no GCN will be present on the site during construction. They anticipate this starting w/c 3rd March 2025 but this is subject to acceptable weather conditions and approval to close the public right of way (an application has been made, pending approval).
  • On-site works: They anticipate on-site works commencing April/May 2025, however a specific date cannot be provided yet as it depends on the length of time they have to trap the site for GCN (which will continue until we have 5 clear days without any GCN being found). At the earliest, they could commence works w/c 7th April but it is likely that this will be closer to May.